Construction Engineering • 5 Marla BOQ • Pakistan 2026 Rates
Pakistan me 5 Marla Ghar ki Tameer ka Kharcha: 2026 BOQ aur Grey Structure Guide
Updated: 17 November 2026 • Verified by Pulse Hatch Civil Engineering Desk
Pakistan me 5 Marla double-storey ghar ki tameer shuru karne se pehle sahi BOQ (Bill of Quantities) banana zaroori hai. Is practical engineering guide me bricks, cement, Grade-60 saria, sand, crush aur thekedar labour rate ka mukammal 2026 hisab pesh kiya gaya hai taake thekedar ke overcharging aur wastage se bacha ja sake.
Language Mode:
Figure 1: Pulse Hatch engineering blueprint showing the exact 2026 BOQ cost & material distribution for 5 Marla house grey structure in Pakistan.
1. 5 Marla Plot Dimensions aur Covered Area ka Sahi Hisab
Pakistan me standard 5 Marla plot ka size aam tor par 25 feet front × 45 feet length (1,125 sq ft) ya modern housing societies (maslan DHA, Bahria Town, CDA Sectors) me 25 feet × 50 feet (1,250 sq ft) hota hai. Double-storey ghar ki planning me covered area ka hisab is tarah banta hai:
📐 Double-Storey Covered Area Breakdown:
Ground Floor: ~1,000 sq ft (Car porch, open lawn aur setbacks chhor kar)
First Floor: ~950 sq ft (Balcony aur terrace chhor kar)
Mumty & Overhead Water Tank: ~200 sq ft
Total Covered Area (Construction Area):2,150 sq ft
Thekedar aksar porch aur mumty ka area full calculate karte hain. Contract sign karte waqt wazeh karein ke boundary walls, open duct aur ramp ka hisab kis tarah hoga.
2. 2026 Grey Structure Materials ki Asal Quantities (BOQ)
Ek standard 2,150 sq.ft covered area ke 5 marla double-storey ghar ke liye structural materials ki exact miqdar:
🧱 Awwal Bricks (Eentein): 48,000 se 52,000 Bricks
9-inch external load-bearing walls aur 4.5-inch internal partition walls ke liye 50,000 awwal eentein lagti hain. 2026 market me Awwal eent ka rate PKR 14.50 se 16.00 per brick chal raha hai. Total Eent Cost: ~PKR 750,000 - 800,000.
📦 Cement Bags (Grade 43/53): 550 se 600 Bags
Bunyad (foundations), masonry (chunaai), dono chaton (RCC roof slabs), lintel beams aur dono taraf ke plaster ke liye 580 bags cement required hota hai. Brands: Fauji, Bestway, ya Maple Leaf. 2026 rate PKR 1,400 se 1,450 per bag hai. Total Cement Cost: ~PKR 810,000 - 850,000.
⚒️ Steel / Saria (Grade 60 Deformed Bar): 3.8 se 4.2 Tons (3,800 - 4,200 kg)
Chaton ke jaal, columns, plinth beams aur overhead water tank ke liye sirf 60-grade deformed bar istemal karein (Mughal Steel, Amreli Steels ya Ittehad). 2026 rate PKR 250,000 se 265,000 per ton chal raha hai. Total Steel Cost: ~PKR 1,000,000 - 1,100,000.
🏗️ Ret (Sand) aur Bajri (Crush):
Sand (Ravi & Chenab): Chunaai aur plaster ke liye taqreeban 3,500 se 4,000 cubic feet ret chahiye (~PKR 150,000 - 180,000). Crush (Margalla / Sargodha 1/2" down): Bunyad aur do RCC chaton ke concrete mix ke liye 1,800 cubic feet bajri chahiye (~PKR 240,000 - 280,000).
👷 Labour Rate (Thekedar Kharcha): PKR 480 se 550 per sq.ft
2,150 sq ft covered area par thekedar ki labour cost PKR 1,050,000 se 1,180,000 banti hai. Isme excavation, masonry, saria bandhai, shuttering aur plaster shamil hota hai.
🔧 Plumbing, Electrical Piping & Termite Proofing:
Dadex/Popular UPVC drainage pipes, PPRC water supply pipes, PVC electrical conduit, switch back boxes aur underground anti-termite chemical spray ka kharcha ~PKR 450,000 - 550,000 ata hai.
Figure 2: Real on-site execution of 5 Marla double-storey house showing RCC roof beam reinforcement and brick masonry.
Aapke budget aur thekedar quotation verification ke liye mukammal itemized summary table:
Material / Item
Estimated Quantity
Unit Rate (2026)
Total Estimated Cost (PKR)
Awwal Bricks
50,000 Bricks
PKR 15.50 / brick
PKR 775,000
Cement (Grade 43/53)
580 Bags
PKR 1,420 / bag
PKR 823,600
Steel (Grade 60 Saria)
4.0 Tons (4,000 kg)
PKR 258,000 / ton
PKR 1,032,000
Sand (Ravi + Chenab)
3,800 cu.ft
Lump sum with cartage
PKR 165,000
Crush (Margalla 1/2" down)
1,800 cu.ft
PKR 145 / cu.ft
PKR 261,000
Labour (Shuttering & Masonry)
2,150 sq.ft
PKR 520 / sq.ft
PKR 1,118,000
Plumbing & Sewerage Piping
Dadex / Master UPVC/PPRC
Material + Plumber
PKR 340,000
Electrical Conduit & Boxes
Piping, DB Boxes, Wires Slab
Material + Electrician
PKR 280,000
Earth Filling (Ghasu) & Excavation
Tractor trolley compaction
Site specific
PKR 140,000
Termite Proofing & Waterproofing
Chemical barrier + Roof Bitumen
Guaranteed treatment
PKR 95,000
Steel Safety Chokhats & Main Gate
16-gauge GI sheet frames
Complete house
PKR 280,000
TOTAL GREY STRUCTURE (2026)
2,150 sq.ft Covered Area
~PKR 2,935 / sq.ft
PKR 6,309,600
💡 Finishing Budget (A-Grade):
Grey structure mukammal hone ke baad finishing (tiles, sanitary fixtures, woodwork doors, kitchens, false ceiling, aluminium windows, paint) par taqreeban PKR 4.5 Million se 5.5 Million mazeed kharcha hota hai. Yani total turnkey A-Grade 5 marla double-storey ghar PKR 10.8M se 12.0M me tayyar hota hai.
4. Thekedar ki Wastage aur 5 Baray Nuqsanat jinse Bachna Zaroori Hai
Ghar banwate waqt clients ko maloomat na hone ki wajah se thekedar lakhoon rupay ka ziyan kar dete hain. In 5 baton par lazmi amal karein:
BBS (Bar Bending Schedule) ke baghair Saria na katwayein: Saria hamesha 40 feet lambai me ata hai. Agar pehle se cutting length plan na ho to saria ke 3 se 4 feet ke tukray zaya ho jate hain jinse 8% tak nuksan hota hai.
Chat ki Terai (Curing) me Kotahi: Slab pour hone ke baad aglay 14 din tak chat par pani ke chotay ponds (kiaris) bana kar pani khara rakhna lazmi hai. Curing na hone se chat me hairline shrinkage cracks par jate hain.
Substandard Steel (Tukra / Rerolled Saria): Sastay saria ke chakar me kache lohay ya unbranded saria na lein. Hamesha Mill-tested Grade 60 deformed bar use karein jiska yield strength 60,000 psi certified ho.
Damp Proof Course (DPC) ki Ghalati: Plinth level par 1.5-inch concrete DPC ke upar bitumen coating aur polythene sheet lazmi lagwayein taake deewaron par saym (dampness) na aaye.
Soil Compaction (Ghasu Bharai): Bunyad me ret ya mitti bharne ke baad paani chhor kar mechanical plate compactor chalwayein. Kachi bharai se 6 mahine baad farsh zameen me dhas jate hain.
Apne 5 Marla Plot ka Custom BOQ Calculate Karein
Pulse Hatch Construction Calculator par apna exact covered area, city aur material grade enter karein aur 1 minute me complete itemized quotation hasil karein.
5 Marla double-storey ghar banane me kitna arsa lagta hai?
Grey structure ki tameer me aam tor par 3.5 se 5 mahine lagte hain (excavation se slab curing tak). Mukammal A-grade finishing ke sath turnkey ghar 7 se 9 mahine me tayyar hota hai.
Kya labour contract par kaam karwana behtar hai ya material ke sath theka dena?
Hamesha Labour Rate Theka behtar hota hai jisme saria, cement aur eentein aap khud khareedte hain aur thekedar sirf mazdoori leta hai. Isse aapko har material ki quality (Grade 60 steel, certified cement) ka 100% control rehta hai.
Islamabad aur Lahore me construction rates me kitna farq hai?
Islamabad/Rawalpindi me Margalla crush qareeb hone ki wajah se bajri sasti hai jabke Lahore me Ravi/Chenab ret sasti hai lekin crush par cartage zyada ata hai. Overall grey structure cost me sirf 3% se 5% ka farq hota hai.
1. 5 Marla Plot Dimensions & Covered Area Estimation
In Pakistan, a standard 5 Marla residential plot measures 25 ft front × 45 ft length (1,125 sq ft) in older sectors, or 25 ft × 50 ft (1,250 sq ft) in modern master-planned communities like DHA, Bahria Town, and CDA Sectors. A well-designed double-storey family layout yields the following covered area:
📐 Architectural Covered Area Distribution:
Ground Floor: ~1,000 sq ft (Accommodating car porch, living hall, kitchen, and 2 bedrooms)
First Floor: ~950 sq ft (Terrace setbacks, 2 bedrooms with attached baths)
Staircase Mumty & Overhead Water Tank: ~200 sq ft
Total Effective Construction Area:2,150 sq ft
Always establish clear contractual definitions with your contractor regarding covered area calculations for boundary walls, open shafts, and car porch projections to avoid billing disputes later.
2. Authentic 2026 Bill of Quantities (BOQ) for Grey Structure
Constructing a 2,150 sq.ft double-storey structure requires precise structural material quantities. Here is the verified engineering benchmark for Pakistan:
🧱 First-Class (Awwal) Bricks: 48,000 to 52,000 Units
For 9-inch perimeter load-bearing masonry and 4.5-inch room partition walls, exactly 50,000 bricks are consumed. Current 2026 kiln prices average PKR 14.50 to 16.00 per brick including delivery. Total Brick Cost: ~PKR 750,000 - 800,000.
📦 Portland Cement: 550 to 600 Bags (Grade 43/53)
Required for foundation concrete, brick mortar, dual suspended RCC slabs (1:2:4 mix), lintels, and internal/external plastering. Reputable brands include Fauji, Bestway, and Maple Leaf. Current rate is PKR 1,400 to 1,450 per bag. Total Cement Cost: ~PKR 810,000 - 850,000.
To resist seismic loads in Zone 2B/3 in Pakistan, exclusively install ASTM A615 Grade 60 steel bar (Mughal, Amreli, or Ittehad). At 2026 market prices of PKR 250,000 to 265,000 per ton, the total steel budget equals ~PKR 1,000,000 - 1,100,000.
🏗️ Aggregates (Sand & Coarse Crush):
River Sand: 3,800 cu.ft of coarse Chenab sand (plaster) and Ravi sand (brick masonry) totals ~PKR 165,000. Margalla Crush: 1,800 cu.ft of 1/2" down graded crush for structural RCC components costs ~PKR 260,000.
👷 Contractor Labour Rate: PKR 480 to 550 per sq.ft
For 2,150 sq ft of covered area, the master contractor labour rate totals PKR 1,050,000 to 1,180,000. This covers excavation, shuttering, rebar tying, casting, and plastering.
Use this verified summary table to cross-examine contractor estimates before executing agreements:
Material / Structural Work
Quantity Consumed
Unit Rate (2026)
Total Cost (PKR)
First-Class (Awwal) Bricks
50,000 Bricks
PKR 15.50 / brick
PKR 775,000
Portland Cement (Grade 43/53)
580 Bags
PKR 1,420 / bag
PKR 823,600
Grade 60 Steel Rebar
4.0 Tons (4,000 kg)
PKR 258,000 / ton
PKR 1,032,000
Sand (Chenab & Ravi)
3,800 cu.ft
Delivered at site
PKR 165,000
Margalla / Sargodha Crush
1,800 cu.ft
PKR 145 / cu.ft
PKR 261,000
Labour Contract (Grey Structure)
2,150 sq.ft
PKR 520 / sq.ft
PKR 1,118,000
Plumbing & Sewerage Infrastructure
UPVC / PPRC Dadex or Master
Turnkey rough-in
PKR 340,000
Electrical Conduit & Slab Boxes
PVC conduit pipes, DB boxes
Labour + Material
PKR 280,000
Earth Filling (Ghasu) & Compaction
Tractor trolley load filling
Site leveled
PKR 140,000
Termite & DPC Waterproofing
Pressure injection + Bitumen felt
Chemical barrier
PKR 95,000
Steel Safety Door Chokhats & Main Gate
16-gauge cold-rolled GI sheets
Complete house
PKR 280,000
TOTAL GREY STRUCTURE BUDGET
2,150 sq.ft Covered Area
~PKR 2,935 / sq.ft
PKR 6,309,600
💡 Finishing Phase Budgeting:
After completing the grey shell, architectural finishes (porcelain tiles, bathroom vanities, solid core doors, modular kitchen cabinets, false ceilings, powder-coated aluminium glazing, and paint) require approximately PKR 4.5 Million to 5.5 Million. Total turnkey move-in cost equals PKR 10.8M to 12.0M.
4. Five Contractor Pitfalls and Material Wastage Risks to Avoid
Unmonitored construction sites experience severe financial and structural leakage. Enforce these five safety rules:
Mandatory Bar Bending Schedule (BBS): Steel bars arrive in standard 40-foot lengths. Without a pre-calculated BBS, ad-hoc cutting produces scrap remnants of 3 to 5 feet, creating a preventable 8% material loss.
Rigorous Concrete Curing (Terai): Newly poured RCC slabs must be submerged under water bunds (kiaris) for a minimum of 14 continuous days. Inadequate hydration induces permanent thermal shrinkage cracking.
Substandard / Re-rolled Saria: Refuse unbranded scrap steel. Only accept ASTM Grade 60 deformed rebar accompanied by mill test certificates verifying 60,000 psi yield strength.
Damp Proof Course (DPC) Integrity: Prevent capillary water rise by applying a continuous double layer of bitumen felt over a 1.5-inch rich concrete DPC layer at the plinth level.
Mechanical Soil Compaction: Foundation earth backfilling must be compacted in 6-inch wet lifts using mechanical plate compactors to prevent floor settlement months after occupancy.
Generate Your Personalized 5 Marla BOQ Estimate
Input your exact covered area, city, and finishing specifications into the Pulse Hatch Construction Calculator for an instant, itemized procurement report.
What is the construction timeline for a 5 Marla double-storey house?
Grey structure completion typically spans 3.5 to 5 months from excavation to the final roof slab curing. Premium turnkey finishing requires an additional 3.5 to 4 months, bringing total completion to 7 to 9 months.
Is a labour-rate contract safer than a material-inclusive turnkey contract?
Yes. Under a labour contract, you procure cement, steel, and bricks directly from authorized distributors, guaranteeing certified Grade 60 saria and fresh cement while eliminating hidden contractor material markups.
Do construction rates vary significantly between Islamabad, Lahore, and Karachi?
Margalla aggregate is cheaper in the Islamabad/Rawalpindi region, whereas sand from Chenab and Ravi carries lower transit costs in Punjab plains. Net grey structure cost variance across major cities remains within 3% to 5%.